Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

“The Solotist” study guide
How did California population become diverse?
Which statement about the elements in the periodic table is true
what was the significance of the legend of sundiata to mahis history
Which of these best describes an advantage of mainstream media over independent media? Corporate censorship prevents public access to information. Mainstream me
Donnovan earned 99 points on his science project. If his grade was a 90%, how many points were possible?PLEASE HELP!!!PLEASSSSSSSSSSSSSSEEEEEE?
which of the following will always determine exactly one triangle
What role did the army play in the railroad strike
Fill in the blank with the correct answer. A) I was ten years old. B) very soon I was ten years old. C) because I was ten years old. D) when I was ten years
Need help to change the sentences to an active voice