if structural steel installed in 2.75 floors of a building 2 3/8 day , how long will it take to install steel in 11 floors

Respuesta :

gentlebiker
gentlebiker gentlebiker
  • 01-08-2017
I will take 9.5 days, to install steel in 11 floors.